Sungrow Fault 105: SPI Auto-Test / Grid Protection Self-Check Failure
Affected Models: Sungrow SG3.0-20RT, SG33-110CX, and SH5.0-10RT Hybrid Series
⚡ Quick Engineering Answer
Sungrow • Fault 105Sungrow Fault 105 indicates a Grid-Side Protection Self-Check (SPI Auto-Test) failure—mandatory under European grid standards such as Italy's CEI 0-21—or an internal EEPROM parameter storage fault on select SH hybrid firmware. Homeowners should perform one external reboot and contact their installer to re-run the auto-test or verify regional grid codes.
📊 Technical Specification & Trigger Matrix
- Official Manual Definition
- The automated pre-connection grid protection relay and trip-time verification routine timed out or failed, blocking utility grid export.
- Trigger Threshold
- Auto-Test trip time deviation beyond grid-code tolerance, or EEPROM CRC mismatch
- Recovery Window
- Stays blocked until Auto-Test passes or parameters are re-initialized
- Subsystem Affected
- Grid Protection Self-Test Logic / Parameter Memory
- Warranty Outlook
- Medium (Misconfigured country code excluded; relay/EEPROM failure covered)
How Sungrow Fault 105 Triggers
Several national electricity regulations—most notably Italy's CEI 0-21 (SPI Interface Protection System)—require solar inverters to execute an automated self-diagnostic sequence (Auto-Test) verifying over/undervoltage and over/underfrequency trip thresholds and relay opening times in milliseconds prior to grid commissioning or parameter changes. Sungrow Fault 105 triggers when this SPI Auto-Test fails to complete within statutory time limits or measures out-of-spec relay response.
On specific Sungrow SH5.0RT–SH10RT firmware variants outside CEI 0-21 regions, Fault 105 can also appear when non-volatile EEPROM configuration storage encounters a parameter read/write checksum mismatch. Because running SPI Auto-Tests, unlocking Grid Guard settings, and re-writing country grid parameters require installer permissions in iSolarCloud, technician involvement is needed whenever an external reboot does not clear the fault.
🔀 Hardware & Series Differences
Triggered if voltage/frequency auto-test trips time out, grid drops mid-test, or wrong country code (Italy CEI 0-21) was accidentally selected.
Occurs if power drops during parameter write or firmware update, corrupting stored protection tables.
🔍 Observable Symptoms
- •Inverter refuses to enter 'Run' / export mode after installation, grid outage, or firmware upgrade.
- •iSolarCloud logs Fault 105 during startup self-testing or mid-way through an Auto-Test routine.
- •Status LED remains flashing red with zero export to the public utility grid.
- •May appear if an installer outside Italy accidentally selected CEI 0-21 during quick setup.
⚙️ Ranked Root Causes
Selecting a region that requires mandatory SPI Auto-Test without running or completing the commissioning wizard leaves the inverter locked in Fault 105.
Grid dips or surges occurring during the multi-minute Auto-Test cycle cause the test timer to fail.
Cutting DC/AC power while writing grid parameters corrupts stored safety tables.
Mechanical relay wear fails the strict trip-time verification required by protection standards.
🔄 Safe Shutdown & Reset Sequence Flow
Follow strict step order left-to-rightTurn OFF the external AC breaker supplying the inverter.
Turn DC (and hybrid battery breaker) OFF and wait 10 minutes for internal memory and capacitors to fully reset.
Switch DC ON first, then AC ON, and wait 5 minutes for startup self-tests to finish.
High-Voltage / Refrigerant Safety Boundary: Pro Service Split
Steps tagged "Homeowner Safe" below are strictly external read-only or external breaker inspections. Steps tagged "Licensed Technician" involve energized DC/AC bus voltages, isolation testing, or sealed refrigerant circuits—never attempt those steps without certification.
🔧 Interactive Step-by-Step Diagnostic Checklist
Check Country Code & Commissioning Status in iSolarCloud
Open iSolarCloud > Device Information and check which Country / Grid Standard is active, plus whether Fault 105 began right after initial install or a firmware update.
Perform One External Cold Power Cycle
Turn AC and DC isolators off for 10 minutes and restart once to rule out a transient startup self-test glitch.
Verify Country Setting, Reflash Firmware & Re-Run SPI Auto-Test
Technician logs in with iSolarCloud installer credentials, confirms the exact regional grid standard, flashes latest firmware if EEPROM mismatch exists, and executes the complete Auto-Test sequence while verifying AC terminal voltage stability.
📋 Ready-to-Send Technician Fault Brief
Completed safe checks without clearing Fault 105? Copy this structured engineering summary for your installer or OEM RMA ticket.
🧰 Field Reference: What Your Technician Will Inspect
For homeowner safety, DIY replacement tools are disabled on this fault code. Your certified electrician or technician should bring:
- •Licensed Installer with iSolarCloud Commissioning Credentials
- •True-RMS Multimeter (for AC Grid Stability Verification)
Don't Risk High-Voltage Shock with Sungrow Fault 105
This fault involves internal bridge or DC intermediate capacitor stages. Under NEC & UL guidelines, probing energized solar conductors can cause lethal arc flash. Get competitive quotes from licensed solar electricians in your postal area:
❓ Frequently Asked Questions
Why did Sungrow Fault 105 appear right after my system was installed?
In regions requiring SPI Auto-Test (like Italy's CEI 0-21), the installer must run and complete the automated grid protection self-test routine before export is permitted—or an incorrect country standard was chosen.
Can a homeowner run the SPI Auto-Test in iSolarCloud?
No. Grid protection parameters and statutory auto-test commissioning tools are restricted to installer accounts for electrical compliance.
Does Fault 105 mean my solar panels are damaged?
No. Fault 105 is purely an AC grid-protection self-test or inverter parameter storage issue; the rooftop solar panels are unaffected.
Related Sungrow Fault Codes
Instantaneous AC grid overvoltage exceeded Sungrow Stage I protection limits, forcing a protective grid relay disconnect until line voltage drops back within statutory range.
The rolling 10-minute average AC voltage at the Sungrow grid terminals exceeded regulatory limits, forcing a temporary grid export pause.
Parallel inverter synchronization timing failed or an internal auxiliary control voltage rail dropped out of tolerance, halting operation.
Excessive DC current component was detected on the inverter AC output lines, indicating asymmetric bridge switching, current-sensor drift, or internal IGBT stress.
Reviewed and verified by the VoltFaults Engineering Standards Team. All diagnostic procedures, safety warnings, and component tests are cross-referenced directly with original manufacturer service documentation and international electrical safety codes (UL 1741, IEEE 1547 & IEC 62109).